In last week’s article I
discussed various reasons that may motivate a Client into undertaking a stock
condition survey and identified a number of key factors that need to considered
prior to engaging a consultant for delivery of the surveys. This week, after a brief explanation of how
data capture has evolved over recent years, I want to view things from ‘the
other side of the fence’ and discuss issues that a consultant may encounter in
both the pre and survey stages.
A short history of data capture
'Older' Psion Handheld Data Collector - Source: http://www.codeo.co.uk/ |
Over recent years
technology had moved on at a rapid pace and there are now numerous hardware and
software packages on the market that enable surveyors to carry out surveys
‘electronically’. I have been lucky
enough to be involved in stock condition surveys over the last 20 years, which
initially were all undertaken on site by hand, usually with a pre-prepared
proforma. This then developed into the
first iteration of electronic data capture in the form Psion handheld’s. These were large ‘bulky’ pieces of equipment
which were difficult to navigate through, and were extremely limited in their
capacity to store data. At the end of
each day it was necessary to upload the information from the handheld via a
docking station, which often led to ‘technical issues’ which sometimes resulted
in data being lost, which was very frustrating.
Battery life was also an issue for Psion handhelds, where it was
necessary to take back up battery packs with us to allow us to stay on
site for a full day. As technology
advanced we started trialling onsite data collection with smaller and slimmer
PDA’s and Palm Pilots. In the early days
these were extremely ‘sluggish’ on site, as the capacity to store data was
often limited. I can remember that one
of my clients had produced a proforma that required recording of so many
attributes that the PDA became unusable. We had to recommend a significant
re-drafting of the proforma in order to be able to continue with the
survey. Nowadays tablet’s have emerged
as the new way of collecting on-site data.
These have built in camera’s, have much larger built in memories, are
light weight and can offer unparalleled back up facilities. With a number of specialist stock survey software
packages available we now have both hardware and software to make the whole
process faster and more efficient. Although it is worth stating that however
advanced hardware and software may become,
the accuracy and value of the data will always come down to the
knowledge and expertise of the surveyor.
Pre-survey stage
It is highly unlikely
that the cost of a stock condition survey will exceed OJEU thresholds therefore
the content of a tender submission will be down to the requirements of each individual
Client. At this stage it is vitally
important for a Consultant to read the tender documents thoroughly to establish the scope of the
survey and therefore assess the resources that will be needed to deliver what
the client is expecting. Although very
significant, resources do not just relate to the survey team. Purchasing hardware and obtaining software
licences can be extremely expensive, which if not adequately considered could
significantly reduce the profitability for the Consultant. Also, a Client is
likely to have their own in house Asset Management system/database and are likely to
require data collected during a stock condition survey to be compatible with
their system. There are numerous examples of asset management software such as
Orchard or Atrium to name a few, however a Consultant will need to become
familiar with a Client’s particular system, which will involve consultation and
possible training. In fact establishing a Client’s existing asset management
processes and systems is fundamental to helping to a Consultant deliver a
successful stock condition survey.
Source: http://www.mdyson.co.uk |
The deadline is also
fundamentally important in planning the survey and also for fee
calculation. A delivery programme should
be formulated at the earliest possibly opportunity, working back from the
client’s deadline. The programme should include all pre and post survey
activities including consultation with the Client, planning, pilot surveys,
training of staff, arranging access, on site surveys, quality assurance checks,
moderation and validation, reporting, etc.
The amount of inspections that are required (which will be determined by
the target sample size) will determine how many surveyors will be needed. It may be that during the preparation of the
programme that a Consultant will realise they will need more surveyors than
they first thought in order to achieve the deadline. This will subsequently
impact on the amount of hardware and software licences that are needed and
therefore the fee that is likely to be charged.
Survey stage
Once a Consultant has
been awarded a contract to deliver a stock condition survey there are number of
things that can be done to ensure that the deadline is met and that the data
collected in accurate and consistent:
Good leadership – It is extremely important that a Consultant appoints an
experienced member of staff to oversee and take charge of the stock survey,
right through to completion. This
individual should have been involved in the tender process and therefore
understand the Client’s requirements, be able to manage a large team of
surveyors, be able to incorporate and manage a robust quality assurance system
and act as liaison with the Client. A Consultant should never underestimate the
complexity of delivering a stock condition survey and unless a suitable
‘leader’ is appointed to manage the project, then the whole process can become
chaotic and poorly managed and will ultimately result in failure.
Training – Quality
of data and consistency are important in ensuring that the data can be
confidently used in the future for a variety of different things. Achieving this however is always one of the
biggest challenges a Consultant will face and one of the biggest frustrations
that a Client will encounter if the information received is of poor
quality. The problem with undertaking
any inspection is that different surveyors could inspect exactly the same
building but actually produce a different assessment of an element or an
attribute. This is human nature and although
impossible to avoid, it is possible to manage.
What a Consultant should be trying to achieve is that surveyors are
looking at elements/attributes in the same way and although they may not arrive
at identical assessments, they should be very similar.
Prior to letting my
surveyors undertake on-site surveys I would give them lots of information
which would include definitions of physical condition, priority, user effect
and risk rating etc. (This would vary from survey to survey, depending on the
Client brief). The table below provides
an example of typical definitions that could be used:
Average Physical
Condition
|
Priority
|
User Effect Rating -
Effect on users of the building
|
Risk Rating - Effect
of condition of the feature/element have on user
|
A -
Good
|
1 -
Urgent Work (0- 3 months )
|
1 -
Significant effect
|
1 -
High Risk
|
B -
Satisfactory
|
2 -
Essential Work (3 - 24 Months )
|
2 -
Some Effect
|
2 -
Medium Risk
|
C -
Poor
|
3 -
Desirable Work (24-60 Months)
|
3 -
Little Effect
|
3 - Low
Risk
|
D- Bad
|
4 Work
not to be carried out Within 5 year plan
|
I would then arrange a half day workshop with the whole survey team, including administration support staff,
where amongst other things we would discuss the definitions and use examples to
assess how individual surveyors would consider a particular element/attribute.
During this meeting we would also discuss and use the hardware/software that
was going to be used for data collection, discuss access issues, time-frames and
the quality assurance procedure. These
types of meeting are invaluable as it gives the survey team the opportunity to
understand what is expected and raise any questions they may have.
Source: http://www.vdpdirect.co.uk |
Quality Assurance
Procedures – As discussed throughout this article, quality
assurance processes are an extremely important part of the whole process. When managing large condition surveys I would
spend a few days out on site with each member of the survey team during the
first few weeks of the survey. This enabled my surveyors to ‘iron out’ any
uncertainties whilst I was present and to ask further questions as needed. When the data was uploaded I was able to view
this through the relevant asset management database and I was able to add
filters so that I could generate numerous reports throughout the whole time
that the data was being collected. I was
then able to question things that appeared to have been missed where data
fields were empty, or ask questions where surveyors had identified high
priority issues etc. This enabled data
to be corrected where necessary and sometimes identified surveyors who I needed
to spend more time with who clearly required more training.
To consider every aspect of a stock condition survey in such a
short article would be impossible.
Hopefully, I have discussed some typical aspects of what can be a
complex process to manage and deliver. Above
all, the success of a stock condition survey will be down to good organisation,
management and leadership which will incorporate all of the various factors I
have discussed above. Once the process
is set up and organised correctly the data collection is usually reasonably
straightforward. In order for this to be achieved there needs to be a great
deal of planning and consultation many months before the data is collected
onsite, if this is not undertaken then a Consultant is likely to encounter
serious difficulties in meeting the expectations of their Client.
Please feel free to share this article and other articles on this site
with friends, family and colleagues who you think would be interested
Information/opinions posted on this site are the
personal views of the author and should not be relied upon by any person or any
third party without first seeking further professional advice. Also,
please scroll down and read the copyright notice at the end of the
blog.
No comments:
Post a Comment