The benefits of using MMC’s are well documented
and include improved quality, speed of delivery, less waste, reduced risk to
health & Safety, minimises disruption etc.
These will vary depending on the method used in addition to the size and
nature of the project. Just like using traditional methods of construction the
benefits of MMC will only be realised if the project is planned and implemented
(and managed) efficiently.
Source: http://www.icfinfo.org.uk/ |
The term Modern
Methods of Construction (MMC) has been used for many years now, to describe
alternative methods of construction and processes that move away from the
traditional methods of masonry construction that we have used historically for many hundreds of years. There are a number of
commonly used and now commonly understood forms of MMC and these include the
likes of off-site fabricated components such as Pre-Cast Concrete, Panellised
Components such as Structurally Insulated Panels (SIPS), Timber Frame,
Volumetric (often referred to as pod construction). There are also a number of MMC’s that are site
based and categorised as non-offsite manufacture methods and these include the
likes of Tunnel Form, Thin Joint and Insulated Concrete Formwork (ICF). There are also hybrid and sub-assemblies and
components that provide additional MMC options, demonstrating that there
is a range of different possibilities offered compared to traditional
construction methods.
ICF offers a number
of advantages compared to traditional construction methods, however the ease
and speed of construction are arguably the biggest advantages. Firstly, the polystyrene blocks, which are
connected with metal or plastic connectors, use semi-skilled labour for
installation. There is no bonding
material such as mortar so the polystyrene formwork can be connected and
installed in a very short period of time, saving money on time and labour. Take a look at the video below to see how ICF
is installed.
The polystyrene formwork is usually constructed to first floor level before it is filled with concrete. Once the concrete has cured, floors (often pre-cast concrete) can be added followed by further polystyrene formwork and eventually a roof, depending upon the height of the construction. The formwork provides excellent thermal efficiency, achieving U values of between 0.30 and 0.11 W/m2K, which are capable of not only achieving, but exceeding current UK Building Regulations requirements. The process of constructing a traditional cavity wall requires external masonry, a cavity with insulation and internal masonry (usually blockwork). This is labour intensive and often time consuming to complete, something that is not such an issue with ICF. Whereas traditional construction may be vulnerable to disruption due to the weather this is also less of an issue with ICF due to the reduced time needed during construction. Once the ICF system has been installed the external walls can then be clad in a variety of different materials. Renders, timber cladding or brick slips are examples of materials that could be used which give the building a modern or traditional appearance from the outside.
How then does ICF compare to
traditional construction from a cost point of view? http://uspace.shef.ac.uk
identify that although initial costs may seem high compared to traditional
construction methods, costs savings will be made due to reduced site
installation time and the use of semi-skilled labour:
‘Perhaps
the main factor that turns many potential ICF builders away from the whole idea
is their headline cost. They appear to be very expensive when compared with
blockwork wall costs. Most ICF systems on sale in the UK cost between £25 and
£35/m²; add ready-mix concrete at £10/m² plus a few extras and you have a wall
cost of well over £40/m² before you have even taken labour into account. In
contrast, blockwork can be built for around £20/m² including labour.
But, as so often happens when you come to cost out
elements of building work, a more thorough comparison shows the ICF cost model
in a very different light. A blockwork wall on its own is only a small part of
the overall wall assembly: it needs an insulated cavity and a waterproof outer
skin, usually built from bricks, stone or a rendered second skin of blockwork.
Also, the joinery openings require steel lintels over them and there is
additional work required with wall ties and cavity closers. A truer figure for
the cost of a brick and block wall is between £70 and £100/m².
In contrast, the labour costs on ICF are very low:
an experienced ICF crew is capable of laying 5m² of wall per hour. Combine this
with an external render coat, costing around £25 or £30/m², and you end up with
a wall cost of between £80 and £90/m², slap bang in the middle of the cost
range for masonry and timber frame walling. But in return, you get very high
energy-efficiency levels built in at no extra cost, good soundproofing,
excellent airtightness and less room for poor detailing, as often happens with
masonry cavity wall work.
Another plus factor for ICF costing stems from the
speed of build, which reduces the preliminary costs of building, the money
spent on fencing, plant and scaffolding. Several of the systems offer the
possibility of building the walls up entirely from the inside, thus further
reducing the need for external scaffolding until much later in the job. ICF no
longer looks expensive and as if to emphasise that point, it is now being taken
up by commercial developers as well as self-builders’
It is clear that ICF
offers a good alternative to traditional construction methods with many
benefits. Perhaps this method of construction will become more commonplace in
the future, particularly as we explore alternatives to traditional
construction. With ever changing
Building Regulations powering a drive for higher thermal efficiency in
buildings and more efficient ways of creating, using and conserving energy,
maybe ICF is a step in the right direction?
Please feel free to share this article and
other articles on this site with friends, family and colleagues who you
think would be interested
Information/opinions
posted on this site are the personal views of the author and should not be
relied upon by any person or any third party without first seeking further
professional advice. Also, please scroll down and read the copyright
notice at the end of the blog.
In addition, consider the quality of the completed product.
ReplyDeleteI have see many masonry block walls cracked from settlement or earth heaving, leaving the owners with an unsightly wall subject to weather, vermin and even vegetation penetration.
To the contrary, an ICF wall is a monolithic, reinforced concrete mass, tied together completely around all corners and openings as well as bonded to the footers, acting as a full height grade beam. It's resistance to settlement or heaving is far superior to block or wood frame,
A further benefit of the double insulated ICF concrete mass wall is its resistance to sound penetration. The interior is left exceptionally quiet, free from intrusion of traffic or other external noise.
Great article as always!
ReplyDeleteHow does such construction fare in the mortgage industry - are banks and building societies willing to accept these non-traditional building methods?
Does anyone know if this construction method is suitable for mid-rise and high-rise buildings? How many stories can be constructed using ICF system? Is there any multi-storey example?
ReplyDelete