Guest
article from John
Peel BSc (Hons) – Assistant Lecturer at
Coventry University
....when things go wrong between other people named in the Contract
the natural reaction is to look in the direction of the Project Manager (PM) to resolve the
issues. It could therefore be argued there is almost an implied duty on the PM
under the NEC to attempt to resolve conflicts before they get to adjudication
Source: http://www.saice.org.za/ |
The role of the Supervisor defined by the NEC
is that of essentially ensuring the works are built in accordance with the
works information. The role of the PM whilst broader in overall scale than that
of the Supervisor is essentially limited (when it comes to defects) to the
actions of the PM under clause 40.6 and 43.4 as well as the duties when
accepting defects under clause 44 and dealing with uncorrected defects under
clause 45.
Why then have I recently been involved in
long winded protracted arguments over defects under the NEC option A contract?
Something must be amiss!
The alarm bells first started to ring when
the Supervisor and Contractor could not agree if a defect actually existed. The
issue related to an element of the works being designed by the Contractor. The
works information contained a specific thickness of material on a drawing but
an overall requirement in specification to build to a specific standard of
thermal efficiency. Both drawing and specification was included in the Works
Information. The Contractor had altered the thickness of material but achieved
the required thermal standard. The Supervisor notified a defect when he
measured the thickness of material and found it to be not the same as stated in
the Works information. The Contractor pointed to the fact the standard had been
achieved and that the difference in material thickness had no adverse impact on
the building. The issue had not been apparent in any design the Contractor had
submitted for acceptance.
The relationship between the Supervisor and
Contractor was already strained at this point and the Supervisor was adamant
that the change in material thickness was not “in accordance with the Works
Information” and as such it was a defect. The notification was duly issued for
the Contractor to correct it. The Contractor then made the argument of
“inconsistency between the documents” under clause 17.1 as the specification
was a performance specification allowing the contractor a degree of flexibility
and the drawing gave a specific thickness thus conflicting with the flexibility in the specification. The Contractor then sought an
instruction from the PM resolving the inconsistency. One interpretation of the
apparent inconsistency was that both documents are read in conjunction with
each other. So the Contractor has the flexibility of the specification to
select products and comply with the standards but the thickness shown in the
drawn information should be adhered to as a minimum and thus there is no
inconsistency. However, playing devil’s advocate one
might also look at the above scenario and think that as long as the Employer is
not in any way at a loss as a result of the change and the performance
standards are complied with then the process of achieving the end result is the
Contractor’s to manage. After all that is essentially part of the process of
design and build.
As PM I could see both sides of the argument.
I suspect that had relationships on the project been better, an amicable
solution could have been found. However, no agreement was reached and with the
defect correction period nearly up the Contractor and Supervisor were becoming
more animated in their dealings with each other. Eventually, I was asked to
decide who was right and who was wrong which brings me to the crux of the matter
from the perspective of the PM.
Contractually there is no role in clause
40-45 for mediation by the PM in disputes over defects. The only negotiation
the PM need actually carry out is that related to agreeing to accept defects.
We could not reach any such agreement in this case because clause 44.2 requires
both the PM and Contractor to agree to consider a change to the works
Information to correct a defect. The Contractor did definitely not agree to any
such change! Ultimately the process would have been to wait until the defect
correction period expired and then apply clause 45 to the matter (dealing with
uncorrected defects). If the Contractor is unhappy with the results he has the
option of Adjudication under the Contract.
However, there is the concept of a spirit of
mutual trust and co-operation to consider. In this instance should the PM
acting in such a spirit mediate between the parties to find an amicable
solution before the matter gets to Adjudication? This is a difficult point
because you cannot “force” co-operation. However, I do believe that all parties
have a duty to co-operate and also foster co-operation in others. When one can
clearly see parties are not co-operating someone should probably step in to
point this out. The onus on the PM to administer most aspects of the Contract
also means that when things go wrong between other people named in the Contract
the natural reaction is to look in the direction of the PM to resolve the
issues. It could therefore be argued there is almost an implied duty on the PM
under the NEC to attempt to resolve conflicts before they get to adjudication.
However, there are areas of the NEC where the
duty of the PM to determine if actions are reasonable, or unnecessary are
expressly stated. For example clause 40.5 require the Supervisor to carry out
tests and inspections without causing “unnecessary delay” to the Work. If the
Contractor believes that in doing tests and inspections the Supervisor has
caused unnecessary delay then he can notify the PM of a compensation event
under clause 60.1.11. It then falls on the PM to determine if the delay was
necessary or unnecessary. The PM must
also decide if other failures by the Supervisor to act in accordance with the
Contract are compensation events although these are far more objective (clause
60.1.6 for example is easy enough to determine simply by looking at the period
for reply and the date of a communication).
In conclusion, the PM takes a backseat to the
Supervisor when it comes to the process of defects management and the role is
strictly speaking limited to a specific few functions. However, the PM might
well become more heavily involved in defect management if the process breaks
down and the parties are no longer able to co-operate or begin to act unreasonably
or cause unnecessary delay. It might well therefore be wise for the PM to take
an active role in overseeing defects management to be able to proactively head
off issues before they deteriorate. This is certainly the lesson I have learnt
the hard way.
Please feel
free to share this article and other articles on this site with friends,
family and colleagues who you think would be interested
Information/opinions
posted on this site are the personal views of the author and should not be
relied upon by any person or any third party without first seeking further
professional advice. Also, please scroll down and read the copyright
notice at the end of the blog.
No comments:
Post a Comment